Offutt AFB Runway Closure Delayed | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.22.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-AffordableFlyers-04.18.24

Airborne-Unlimited-04.19.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Wed, Aug 28, 2019

Offutt AFB Runway Closure Delayed

Will Maximize Construction Ahead Of Winter Months

The 55th Wing’s runway replacement at Offutt Air Force Base has been pushed back from December 2019 to October 2020.

The ten-month delay of the runway closure allows for demolition and earthwork to begin before winter. This sets up the program to be in the asphalt and concrete work phase by spring 2021 and wrapping up the needed inspections and Federal Aviation Administration approval to reopen in the twelfth month of work.

Sections of Offutt AFB’s current runway are more than 70 years old. Regular maintenance is required to sustain safe flight conditions. The replacement, which is projected to cost approximately $176 million between Offutt AFB and Lincoln Airport (LNK), sets up the 55th Wing’s global intelligence, surveillance and reconnaissance mission to continue from Offutt AFB for at least 20 years before any major maintenance is required.

“It is definitely needed. (The 55th Civil Engineer Squadron) is pouring man-hours and resources into our current runway just to keep it functioning,” said Rob Hufford, 55th CES civil engineer and 55th Wing Project Management Office engineering lead. “As it ages we have to put more time and money into it, but we still have the same amount of people and the same amount of money."

The finished product is planned to be built narrower but with the same length. Features of the new runway design include concrete landing zones with an asphalt center and shoulders.

“The design we are going with is the model bases are going to across the Air Force where we can,” Hufford said. “It’s faster to construct and it's, in theory, easier to maintain. We can go through and do asphalt repairs in a couple hours, and it's good to go. Whereas with concrete, you need a couple of days.”

During the replacement, the wing plans to move flight operations to LNK which is just under 50 miles away.

“One of our driving factors is to protect the Airmen here at Offutt AFB, from being gone longer than 12 months,” Hufford said. “We know it's going to stink to have to go back and forth from Lincoln on a daily basis, so that's why we are trying to limit how long that displacement occurs.”

Commuting to and operating from LNK’s west ramp is estimated to last for approximately 12 months. Nearly 800 personnel are expected to be bused between Offutt AFB and LNK daily until construction is completed in October of 2021.

“The 55th Maintenance Group’s main concerns revolve around the support for our people while deployed to Lincoln,” said Capt. Scott Yancey, 83rd Aircraft Maintenance Unit officer in charge. “We will be working extra-long shifts, four days per week, with three day breaks. Our highly trained Airmen are critical to keeping the maintenance machine moving which is why taking care of our people is our highest priority.”

Preparations are being made at the west ramp at LNK to meet the demands of the Offutt AFB’s aircraft. The apron is being reconditioned, a temporary hangar is being erected and renovations are being made to an existing hangar and firehouse.

(Image provided with USAF news release)

FMI: www.af.mil

Advertisement

More News

ANN's Daily Aero-Term (04.26.24): DETRESFA (Distress Phrase)

DETRESFA (Distress Phrase) The code word used to designate an emergency phase wherein there is reasonable certainty that an aircraft and its occupants are threatened by grave and i>[...]

ANN's Daily Aero-Linx (04.26.24)

Aero Linx: The International Association of Missionary Aviation (IAMA) The International Association of Missionary Aviation (IAMA) is comprised of Mission organizations, flight sch>[...]

Airborne 04.22.24: Rotor X Worsens, Airport Fees 4 FNB?, USMC Drone Pilot

Also: EP Systems' Battery, Boeing SAF, Repeat TBM 960 Order, Japan Coast Guard H225 Buy Despite nearly 100 complaints totaling millions of dollars of potential fraud, combined with>[...]

Airborne 04.24.24: INTEGRAL E, Elixir USA, M700 RVSM

Also: Viasat-uAvionix, UL94 Fuel Investigation, AF Materiel Command, NTSB Safety Alert Norges Luftsportforbund chose Aura Aero's little 2-seater in electric trim for their next gli>[...]

Airborne-NextGen 04.23.24: UAVOS UVH 170, magni650 Engine, World eVTOL Directory

Also: Moya Delivery Drone, USMC Drone Pilot, Inversion RAY Reentry Vehicle, RapidFlight UAVOS has recently achieved a significant milestone in public safety and emergency services >[...]