Fri, Jan 07, 2011
Early February Launch Opportunity Delayed as Work Continues on
External Tank
The Space Shuttle Program held its weekly Program Requirements
Control Board (PRCB) meeting today to review progress on the
continuing engineering investigation, testing and analysis
regarding shuttle Discovery's external fuel tank stringer crack
issue.
With the work remaining, the potential for additional
modifications yet to be defined, and further reviews pending, the
decision was made today to allow the teams additional time and
delay the next launch opportunity out of the early February launch
window, which opened Feb. 3. New potential launch dates for
Discovery’s STS-133 mission and shuttle Endeavour’s
STS-134 mission will be discussed at next Thursday’s PRCB
meeting.
Progress continues to be made in understanding the most probable
cause of cracks discovered on Discovery’s external tank
mid-section, known as the intertank, where small cracks developed
during the Nov. 5, 2010, launch attempt. Four additional small
cracks were found during thorough X-ray image scans of the backside
of the tank after Discovery was returned from the launch pad to the
Vehicle Assembly Building at NASA’s Kennedy Space Center in
Florida on Dec. 22.
Plans are for the repair work to continue through the weekend.
The shuttle program also reviewed the plan to modify as many as 32
additional stringers with radius blocks, which will provide added
structural support in areas known to carry much of the structural
load of the external tank. These radius blocks essentially fit over
existing stringer edges through which the securing rivets are
installed to provide additional structural support. The radius
block modification is a known and practiced structural augmentation
technique used extensively on the intertank. This work should begin
as soon as the repairs to the three stringers with the four
additional small cracks have been completed, likely in the next day
or so, and the modification of the additional 32 stringers is
expected to be complete next week.
Senior NASA managers and Space Shuttle Program managers will
meet Monday to review the progress to date and the forward plan. A
determination of the need and viability for the installation of
additional radius blocks on all remaining stringers will be made
sometime next week.
More News
From 2023 (YouTube Version): Legacy of a Titan Robert (Bob) Anderson Hoover was a fighter pilot, test pilot, flight instructor, and air show superstar. More so, Bob Hoover was an i>[...]
Get The Latest in Aviation News NOW on Instagram Are you on Instagram yet? It's been around for a few years, quietly picking up traction mostly thanks to everybody's new obsession >[...]
Aero Linx: B-52H Stratofortress The B-52H Stratofortress is a long-range, heavy bomber that can perform a variety of missions. The bomber is capable of flying at high subsonic spee>[...]
Altimeter Setting The barometric pressure reading used to adjust a pressure altimeter for variations in existing atmospheric pressure or to the standard altimeter setting (29.92).>[...]
"Knowing that we play an active part in bettering people's lives is extremely rewarding. My team and I are very thankful for the opportunity to be here and to help in any way we ca>[...]