Continued Delays May Bring Significant Change
Labor unions may be poised for a huge "I told you so" at
Boeing's expense. BusinessWeek reports that after four major delays
and two lost years, Boeing is rethinking its strategy of
outsourcing so much the construction of its new 787 Dreamliner.
IAM members made limits on outsourcing a major bargaining issue
in the settlement of their 58-day strike against the company last
year. Boeing engineers say problems with partners have forced the
company to repeatedly send staffers out to suppliers to resolve
issues.
The first 787 flight was originally supposed to happen in August
2007. Boeing now hopes to make that happen by this June, with first
deliveries now projected for Spring of 2010.
In planning for future variants of the 787, Boeing appears to be
reducing reliance on outsourcing. That shift could upset the plans
of companies worldwide, but Boeing Commercial Airplanes CEO Scott
Carson was clear in comments to reporters in November.
"We fully recognize that we made some mistakes... on the 787-9,
we are pulling more of the engineering back inside to try and
alleviate some of the issues we've had," Carson said.
Engineering VP Mike Denton has also weighed in on the matter.
"Our engineers and production workers are basically correcting the
problems that should have never come to us in the first place," he
said. "We will probably do more of the design and even some of the
major production for the next new airplanes ourselves as opposed to
having it all out with the partners."
Boeing hasn't publicly confirmed a significant shift with its
plans... but
with customers increasingly skeptical about Boeing's
delivery timeframes for the oft-delayed Dreamliner, it
may only be a matter of time.
More News
From 2023 (YouTube Version): Legacy of a Titan Robert (Bob) Anderson Hoover was a fighter pilot, test pilot, flight instructor, and air show superstar. More so, Bob Hoover was an i>[...]
Get The Latest in Aviation News NOW on Instagram Are you on Instagram yet? It's been around for a few years, quietly picking up traction mostly thanks to everybody's new obsession >[...]
Aero Linx: B-52H Stratofortress The B-52H Stratofortress is a long-range, heavy bomber that can perform a variety of missions. The bomber is capable of flying at high subsonic spee>[...]
Altimeter Setting The barometric pressure reading used to adjust a pressure altimeter for variations in existing atmospheric pressure or to the standard altimeter setting (29.92).>[...]
"Knowing that we play an active part in bettering people's lives is extremely rewarding. My team and I are very thankful for the opportunity to be here and to help in any way we ca>[...]