787 Horizontal Stab Structure Test A Success | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.22.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-AffordableFlyers-04.18.24

Airborne-Unlimited-04.19.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Thu, Jul 03, 2008

787 Horizontal Stab Structure Test A Success

Some Good News From Alenia Aeronautica

After seeing its Global Aeronautica joint-venture with Boeing in the news twice in as many days due to production-related issues, Alenia Aeronautica was ready for some good news. The company reported Wednesday it successfully completed destructive testing on the horizontal stabilizer of the Boeing 787 Dreamliner.

The test took place at Alenia's Pomigliano plant in Naples with Boeing engineers and representatives of the US Federal Aviation Administration (FAA) and European Aviation Safety Agency (EASA) in attendance. The stabilizer is made at the Alenia Aeronautica plant at Foggia in Italy's Puglia region.

Previous physical testing had shown that the horizontal stabilizer meets its certification requirement to withstand 150 percent of the maximum aerodynamic load it ever could encounter in flight. Once Alenia engineers proved that, they then pushed it to the limit -- testing the horizontal stabilizer to see just much load the horizontal stabilizer could withstand before failure.

In that test, the structure did not break until well in excess of the required 150 percent of limit load. The destructive test was the culmination of seven months of testing conducted by Alenia and Boeing.

"This is quite an achievement," said Nazario Cauceglia, Alenia Aeronautica's chief technical officer. "The test validates the innovative multispar design concept and consolidates the spirit of cooperation established between Alenia and Boeing engineers on this difficult task, and on the entire 787 program."

"Successful completion of the 787 horizontal stabilizer failure test marks the culmination of an innovative design and development activity," said Randy Harley, vice president and general manager, 787 Engineering and Technology. "Working together, the 787 team has once again confirmed the power of an integrated partnership."

Previous tests at Pomigliano gauged the structure's capability to withstand various extremes in aerodynamic pressures, such as upward and downward deflection and extreme asymmetric loads.

With static testing complete, Alenia now will proceed to fatigue testing. Alenia engineers at Pomigliano will subject a complete horizontal stabilizer to repeated flexing, meant to demonstrate the stabilizer's ability to carry repeated operational load cycles representative of its design life.

To obtain certification, the tail will be tested to at least three times its design life. The testing program is slated to conclude with Boeing conducting a bird strike test at its facilities in the US.

FMI: www.alenia-aeronautica.it/, www.boeing.com

Advertisement

More News

ANN's Daily Aero-Term (04.25.24): Airport Rotating Beacon

Airport Rotating Beacon A visual NAVAID operated at many airports. At civil airports, alternating white and green flashes indicate the location of the airport. At military airports>[...]

ANN's Daily Aero-Linx (04.25.24)

Aero Linx: Fly for the Culture Fly For the Culture, Inc. is a 501(c)(3) non-profit organization that serves young people interested in pursuing professions in the aviation industry>[...]

Klyde Morris (04.22.24)

Klyde Is Having Some Issues Comprehending The Fed's Priorities FMI: www.klydemorris.com>[...]

Airborne 04.24.24: INTEGRAL E, Elixir USA, M700 RVSM

Also: Viasat-uAvionix, UL94 Fuel Investigation, AF Materiel Command, NTSB Safety Alert Norges Luftsportforbund chose Aura Aero's little 2-seater in electric trim for their next gli>[...]

Airborne 04.22.24: Rotor X Worsens, Airport Fees 4 FNB?, USMC Drone Pilot

Also: EP Systems' Battery, Boeing SAF, Repeat TBM 960 Order, Japan Coast Guard H225 Buy Despite nearly 100 complaints totaling millions of dollars of potential fraud, combined with>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC