NASA's Dawn Spacecraft Arrives In Florida | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.22.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-AffordableFlyers-04.18.24

Airborne-Unlimited-04.19.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Tue, Apr 10, 2007

NASA's Dawn Spacecraft Arrives In Florida

Just A Little After Dawn, In Fact

NASA tells ANN the Dawn spacecraft arrived at Astrotech Space Operations in Titusville, FL at 0900 EDT Tuesday morning. Dawn, NASA's mission into the heart of the asteroid belt, is at the facility for final processing and launch operations. Dawn's launch period opens June 30.

"Dawn only has two more trips to make," said Dawn project manager Keyur Patel of NASA's Jet Propulsion Laboratory in Pasadena, CA. "One will be in mid-June when it makes the 15-mile journey from the processing facility to the launch pad. The second will be when Dawn rises to begin its eight-year, 3.2-billion-mile odyssey into the heart of the asteroid belt."

The Dawn spacecraft will employ ion propulsion to explore two of the asteroid belt's most intriguing and dissimilar occupants: asteroid Vesta and the dwarf planet Ceres.

As Aero-News has reported, NASA scrapped the Dawn program in March 2006, citing cost overruns and technical glitches. The program was given new life weeks later, due in large part to protests from scientists and engineers at JPL.

Now that Dawn has arrived at Astrotech near NASA's Kennedy Space Center, final prelaunch processing will begin. Technicians will install the spacecraft's batteries, check out the control thrusters and test the spacecraft's instruments. In late April, Dawn's large solar arrays will be attached and then deployed for testing. In early May, a compatibility test will be performed with the Deep Space Network used for tracking and communications.

Dawn will then be loaded with fuel to be used for spacecraft control during the mission. Finally, in mid-May, the spacecraft will undergo spin-balance testing. Dawn will then be mated to the upper stage booster and installed into a spacecraft transportation canister for the trip to Cape Canaveral Air Force Station. This is currently scheduled for June 19, when it will be mated to the Delta II rocket at Pad 17-B.

The rocket that will launch Dawn is a Delta II 7925-H manufactured by the United Launch Alliance; it is a heavier-lift model of the standard Delta II that uses larger solid rocket boosters. The first stage is scheduled to be erected on Pad 17-B in late May. Then the nine strap-on solid rocket boosters will be raised and attached. The second stage, which burns hypergolic propellants, will be hoisted atop the first stage in the first week of June. The fairing which surrounds the spacecraft will then be hoisted into the clean room of the mobile service tower.

Next, engineers will perform several tests of the Delta II. In mid-June, as a leak check, the first stage will be loaded with liquid oxygen during a simulated countdown. The next day, a simulated flight test will be performed, simulating the vehicle's post-liftoff flight events without fuel aboard. The electrical and mechanical systems of the entire Delta II will be exercised during this test.

Once the Dawn payload is atop the launch vehicle, a final major test will be conducted: an integrated test of the Delta II and Dawn working together. This will be a combined minus and plus count, simulating all events as they will occur on launch day, but without propellants aboard the vehicle.

FMI: http://dawn.jpl.nasa.gov

Advertisement

More News

ANN's Daily Aero-Term (04.26.24): DETRESFA (Distress Phrase)

DETRESFA (Distress Phrase) The code word used to designate an emergency phase wherein there is reasonable certainty that an aircraft and its occupants are threatened by grave and i>[...]

ANN's Daily Aero-Linx (04.26.24)

Aero Linx: The International Association of Missionary Aviation (IAMA) The International Association of Missionary Aviation (IAMA) is comprised of Mission organizations, flight sch>[...]

Airborne 04.22.24: Rotor X Worsens, Airport Fees 4 FNB?, USMC Drone Pilot

Also: EP Systems' Battery, Boeing SAF, Repeat TBM 960 Order, Japan Coast Guard H225 Buy Despite nearly 100 complaints totaling millions of dollars of potential fraud, combined with>[...]

Airborne 04.24.24: INTEGRAL E, Elixir USA, M700 RVSM

Also: Viasat-uAvionix, UL94 Fuel Investigation, AF Materiel Command, NTSB Safety Alert Norges Luftsportforbund chose Aura Aero's little 2-seater in electric trim for their next gli>[...]

Airborne-NextGen 04.23.24: UAVOS UVH 170, magni650 Engine, World eVTOL Directory

Also: Moya Delivery Drone, USMC Drone Pilot, Inversion RAY Reentry Vehicle, RapidFlight UAVOS has recently achieved a significant milestone in public safety and emergency services >[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC