Boeing Drops A Bomb: 787 Delayed For Third Time | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.01.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-Unlimited-04.11.24

Airborne-Unlimited-04.12.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Wed, Apr 09, 2008

Boeing Drops A Bomb: 787 Delayed For Third Time

First Flight Now Q4 2008; Deliveries In Q3 '09

It's not really unexpected... but it's still a major blow to Boeing's struggling 787 Dreamliner program. Moments ago, the American planemaker announced a revised plan for first flight and initial deliveries of the 787, that moves target dates for those milestones off by as much as six months beyond earlier expectations.

While noting significant progress has been made assembling Airplane #1 -- the aircraft unveiled with great fanfare last July -- Boeing says first flight is being rescheduled due to slower than expected completion of work that traveled from supplier facilities into Boeing's final assembly line, unanticipated rework, and the addition of margin into the testing schedule.

"The new delivery schedule is based on a more conservative production plan developed with the 787 partner team," said the planemaker, which now targets "approximately" 25 deliveries in 2009.

First flight of the composite-bodied airplane will move into the fourth quarter of this year rather than the end of the second quarter, and first delivery is now planned for the third quarter of 2009 instead of first quarter.

Despite the ominous nature of Boeing's announcement -- this is the third time Boeing has been forced to delay the Dreamliner's progress, due to production-related issues -- company officials expressed confidence in the new plan and the steps being taken to accelerate program performance.

"Over the past few months, we have taken strong actions to confront and overcome start-up issues on the program, and we have made solid progress," said Boeing Commercial Airplanes President and CEO Scott Carson. "Nevertheless, the traveled work situation and some unanticipated rework have prevented us from hitting the milestones we laid out in January. Our revised schedule is built upon an achievable, high-confidence plan for getting us to our power-on and first-flight milestones. Also, while the fundamental technologies and design of the 787 remain sound, we have inserted some additional schedule margin for dealing with other issues we may uncover in testing prior to first flight and in the flight test program."

As ANN reported, the company said in January it would be conducting a comprehensive assessment of its supply chain and production system capabilities to determine the details of the 787's flight test program and initial delivery profile.

As a result of that assessment, the first-year delivery plan announced Wednesday will be followed by what Boeing terms "a more gradual ramp up to full-rate production than previously planned."

"We deeply regret the disruption and disappointment these changes will cause for our customers, and we will work closely with each of them to minimize the impact," said Carson. "We have taken significant action to improve supply chain and production system performance, such as our investment in Global Aeronautica, but based on our assessment, the prudent course is to proceed with a more gradual ramp up to full-rate production."

Pat Shanahan, 787 vice president and program manager, echoed Carson's comments about the progress being made in 787 factories.

"The work that remains to be done on Airplane #1 is well defined, and we can see our way to -- and have confidence in -- the new milestones we have set for it," said Shanahan. "We have addressed the major challenges that slowed our progress while trying to complete the primary structure -- the parts shortages, engineering changes, and manufacturing changes -- and we are well into the systems installation that is the precursor to putting power on the airplane for the first time. We have also worked closely with our partners to achieve higher levels of completion of their parts of subsequent airplanes, and we will continue to drive improvements in the supply chain and production system performance," he said.

For tracking program progress, Shanahan outlined a series of milestones that will occur before June 30: 787 static and fatigue structural test airplanes will move to their testing locations; Airplanes #3 and #4 will enter final assembly; hardware airworthiness qualifications will be complete; and power on will be achieved.

Shanahan also said the program has changed the timing of the introduction of two 787 derivatives. The 787-9, a larger variant of the airplane, will be the first derivative of the baseline 787 with delivery planned for early 2012. The 787-3, a shorter-range model previously slated to deliver in 2010, will now become the second derivative of the airplane family.

While research and development costs will likely increase as a result of the 787 schedule change, Boeing says it expects no change to 2008 earnings guidance.

FMI: www.boeing.com

Advertisement

More News

ANN's Daily Aero-Linx (04.15.24)

Aero Linx: International Flying Farmers IFF is a not-for-profit organization started in 1944 by farmers who were also private pilots. We have members all across the United States a>[...]

Classic Aero-TV: 'No Other Options' -- The Israeli Air Force's Danny Shapira

From 2017 (YouTube Version): Remembrances Of An Israeli Air Force Test Pilot Early in 2016, ANN contributor Maxine Scheer traveled to Israel, where she had the opportunity to sit d>[...]

Aero-News: Quote of the Day (04.15.24)

"We renegotiated what our debt restructuring is on a lot of our debts, mostly with the family. Those debts are going to be converted into equity..." Source: Excerpts from a short v>[...]

Airborne 04.16.24: RV Update, Affordable Flying Expo, Diamond Lil

Also: B-29 Superfortress Reunion, FAA Wants Controllers, Spirit Airlines Pulls Back, Gogo Galileo Van's Aircraft posted a short video recapping the goings-on around their reorganiz>[...]

ANN's Daily Aero-Term (04.16.24): Chart Supplement US

Chart Supplement US A flight information publication designed for use with appropriate IFR or VFR charts which contains data on all airports, seaplane bases, and heliports open to >[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC