GAO Not 'Sold' on Raptor Program | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.22.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-AffordableFlyers-04.18.24

Airborne-Unlimited-04.19.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Tue, Mar 18, 2003

GAO Not 'Sold' on Raptor Program

Delays, Missed Cost Targets, Make GAO Recommend 'Go Slow'

The Government Accounting Office is skeptical about the F/A-22 Raptor. In its recently-released report, it tells us why, as these verbatim excerpts show [emphases added]:

The Air Force is developing the F/A-22 aircraft to fly at higher speeds for longer distances, be less detectable, and improve the pilot’s awareness of the surrounding situation. The F/A-22 will replace the Air Force’s existing fleet of F-15 aircraft. Over the past several years the program has experienced significant cost overruns and schedule delays.

Congress mandated that GAO assess the development program and determine whether the Air Force is meeting key performance, schedule, and cost goals. GAO also assessed the implications of the progress of the development program on production.

The F/A-22 development program did not meet key performance, schedule, and cost goals in fiscal year 2002, and delays in the flight test program have led to an increase in the development cost estimate of $876 million. In response to this increase, DOD restructured the development program and reduced production aircraft by 27. If additional delays occur, further changes may be required. The program also continues to address technical problems that have limited the performance of test aircraft, including violent movement or "buffeting" of the vertical fins, overheating in portions of the aircraft, weakening of materials in the horizontal tail, and instability of avionics software. Air Force officials cannot predict when they will resolve these problems. These technical problems, along with the late delivery of aircraft to the flight test center, have delayed the development program.

Based on F/A-22 flight test accomplishment data and current flight test plans, we believe that operational testing will likely be delayed several months beyond the planned August 2003 start date.

The F/A-22 program is in its final stages of development, and low-rate initial production has begun. Since fiscal year 1997, funds have been appropriated to acquire production aircraft, and the F/A-22 acquisition plan calls for steadily increasing annual production rates. However, GAO considers the Air Force’s acquisition strategy at high risk for increases in production costs.

In past reports, GAO has reported that acquiring aircraft while significant technical challenges remain does not allow for adequate testing of the aircraft. The uncertainties regarding performance capabilities of the F/A-22 aircraft and its development schedule will persist until technical problems have been addressed, including testing of modifications or fixes necessary to potentially alleviate these problems. In light of those uncertainties, steadily increasing annual production rates could result in the Air Force having to modify a larger quantity of aircraft after they are built.

To help minimize the risks of producing large quantities of aircraft that may require costly modifications, GAO recommends that the Secretary of Defense

  1. reconsider the decision to increase the annual production rate beyond 16 aircraft until greater knowledge on any need for modifications is established through completion of operational testing and
  2. update the 2002 risk assessment and certification with sufficient detail to allow verification of the conclusions.

In comments on a draft of this report, the Department of Defense (DOD) stated that it agreed, for the most part, with our description of the current state of the F/A-22 program’s content, schedule and cost. However, DOD did not concur with our recommendation.

FMI: www.gao.gov/cgi-bin/getrpt?GAO-03-431

Advertisement

More News

Airborne 04.16.24: RV Update, Affordable Flying Expo, Diamond Lil

Also: B-29 Superfortress Reunion, FAA Wants Controllers, Spirit Airlines Pulls Back, Gogo Galileo Van's Aircraft posted a short video recapping the goings-on around their reorganiz>[...]

ANN's Daily Aero-Term (04.20.24): Light Gun

Light Gun A handheld directional light signaling device which emits a brilliant narrow beam of white, green, or red light as selected by the tower controller. The color and type of>[...]

Aero-News: Quote of the Day (04.20.24)

"The journey to this achievement started nearly a decade ago when a freshly commissioned Gentry, driven by a fascination with new technologies and a desire to contribute significan>[...]

Aero-News: Quote of the Day (04.21.24)

"Our driven and innovative team of military and civilian Airmen delivers combat power daily, ensuring our nation is ready today and tomorrow." Source: General Duke Richardson, AFMC>[...]

ANN's Daily Aero-Term (04.21.24): Aircraft Conflict

Aircraft Conflict Predicted conflict, within EDST of two aircraft, or between aircraft and airspace. A Red alert is used for conflicts when the predicted minimum separation is 5 na>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC