Early February Launch Opportunity Delayed as Work Continues on
External Tank
The Space Shuttle Program held its weekly Program Requirements
Control Board (PRCB) meeting today to review progress on the
continuing engineering investigation, testing and analysis
regarding shuttle Discovery's external fuel tank stringer crack
issue.
With the work remaining, the potential for additional
modifications yet to be defined, and further reviews pending, the
decision was made today to allow the teams additional time and
delay the next launch opportunity out of the early February launch
window, which opened Feb. 3. New potential launch dates for
Discovery’s STS-133 mission and shuttle Endeavour’s
STS-134 mission will be discussed at next Thursday’s PRCB
meeting.
Progress continues to be made in understanding the most probable
cause of cracks discovered on Discovery’s external tank
mid-section, known as the intertank, where small cracks developed
during the Nov. 5, 2010, launch attempt. Four additional small
cracks were found during thorough X-ray image scans of the backside
of the tank after Discovery was returned from the launch pad to the
Vehicle Assembly Building at NASA’s Kennedy Space Center in
Florida on Dec. 22.
Plans are for the repair work to continue through the weekend.
The shuttle program also reviewed the plan to modify as many as 32
additional stringers with radius blocks, which will provide added
structural support in areas known to carry much of the structural
load of the external tank. These radius blocks essentially fit over
existing stringer edges through which the securing rivets are
installed to provide additional structural support. The radius
block modification is a known and practiced structural augmentation
technique used extensively on the intertank. This work should begin
as soon as the repairs to the three stringers with the four
additional small cracks have been completed, likely in the next day
or so, and the modification of the additional 32 stringers is
expected to be complete next week.
Senior NASA managers and Space Shuttle Program managers will
meet Monday to review the progress to date and the forward plan. A
determination of the need and viability for the installation of
additional radius blocks on all remaining stringers will be made
sometime next week.
More News
Chaff Thin, narrow metallic reflectors of various lengths and frequency responses, used to reflect radar energy. These reflectors, when dropped from aircraft and allowed to drift d>[...]
“Today, XB-1 took flight in the same hallowed airspace where the Bell X-1 first broke the sound barrier in 1947. I’ve been looking forward to this flight since founding>[...]
“Teaming up with the EAA and Berlin Express for this event in Cincinnati will give warbird fans a unique opportunity to see the aircraft that helped defend freedom and gave t>[...]
Hazardous Weather Information Summary of significant meteorological information (SIGMET/WS), convective significant meteorological information (convective SIGMET/WST), urgent pilot>[...]
Aero Linx: The Nebraska Aeronautics Commission The Nebraska Aeronautics Commission was created by the 1935 Legislature to oversee the development of aviation in the state. The Comm>[...]