DOT IG: FAA NextGen Metroplex Initiative Delayed | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Recent Daily Episodes

Episode Date

AMA Drone Report

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday

Airborne-Thursday

Airborne-Friday

Airborne-Unmanned w/AUVSI

Airborne On ANN

AMA 08.17.17

Airborne 08.14.17

Airborne 08.15.17

Airborne 08.16.17

Airborne 08.17.17

Airborne 08.18.17

Airborne-Unmanned 08.15.17

Airborne-YouTube

AMA 08.17.17

Airborne 08.14.17

Airborne 08.15.17

Airborne 08.16.17

Airborne 08.17.17

Airborne 08.18.17

Airborne-Unmanned 08.15.17

NEW!!! 2017 AirVenture Innovation Preview -- YouTube Presentation / Vimeo Presentation

Tue, Aug 14, 2012

DOT IG: FAA NextGen Metroplex Initiative Delayed

Expected Completion Currently 15 Months Behind Schedule

A report released by the DOT Inspector General indicates that the FAA's "Metroplex" initiative, which is intended to get NextGen up and running in major metropolitan areas, is currently about 15 months behind schedule.

In the report, the IG acknowledges that the FAA quickly added the recommendations that followed a 2009 Radio Technical Commission for Aeronautics (RTCA) study into its budgets and strategic plans, and set up a process for ongoing industry collaboration. But "(w)hile FAA has focused on one of the most critical recommendations—metroplex airspace—it missed milestones at the first two sites due to unresolved staffing issues and lack of a project plan. The expected completion date for all metroplex sites is now 15 months later than FAA’s earlier, more aggressive plans. Further, industry representatives are concerned that the effort may not deliver all planned/desired benefits since FAA has focused only on near-term airspace and procedure improvements rather than maximizing new technologies and advanced procedures as recommended by the task force. For example, of the 136 metroplex solutions proposed for the first 7 metroplex sites, only 3 are for the more advanced procedures that allow aircraft to fly more precise routes and curved approaches to airports.

"FAA has not yet resolved many of the barriers that will impede the implementation of the task force recommendations. These barriers include working across diverse agency lines of businesses, updating policies, streamlining the process for implementing new flight procedures, applying environmental regulations, upgrading controller automation tools, and training controllers on new advanced procedures."

The IG found that airline representatives are concerned that the FAA has not yet clearly defined expected benefits for proposed metroplex activities and that maximum benefits—shorter flight paths and fuel savings—may not be achievable. This is important to the airlines who are key stakeholders in the metroplex initiative. The IG also reported that firm estimates of benefits of NextGen have not yet been established, and that the agency does not have a clear process that ensures all projects are properly reviewed and prioritized.

The DOT IG issued a series of recommendations to the FAA to address the delays, which met with mixed reviews from the agency. The IG said that "(t)o provide a solid foundation for NextGen, FAA must resolve the safety, policy, training, and organizational issues addressed by the task force. Further, both Government and industry must synchronize their planning and implementation efforts to effectively roll out NextGen initiatives and realize tangible benefits. Continued uncertainty about these efforts could undermine industry’s commitment to investing in NextGen technology—a critical element for successful implementation."

FMI: Read the Report
 

Advertisement

More News

ONE Aviation 'Canada' Program Unveils First Developmental Airframe

One Of A Series Of Sequential Prototypes Will Help Develop The Forthcoming EA-700 The ONE Aviation 'Canada' program, which ANN exclusively detailed last year for the first time, is>[...]

Garmin Receives EASA Approval For New GTN 650/750 Features

Tailored Specifically For European Operators Garmin is pleased to announce an expanded feature set, an enhanced user interface and additional wireless connectivity solutions for it>[...]

Airborne-Unmanned 08.15.17: Reno Drone Races, DoD CrackDown, Blue Angels v UAV?

Also: Kansas DOT-AirMap, CIRRUAS Drone Program, Daytona Beach PD UAS, Virginia UAS SAR The Reno Air Racing Association has signed an agreement with the MultiGP Drone Racing League >[...]

RFP: ANN Seeking New Site/Facility For Major Studio Upgrade

It's Official: Aggressive Upgrades For New Airborne Programs WILL Require New Digs It's been in development for years, but we're getting to a point where we think we can pull off s>[...]

Airborne 08.17.17: GA Sales Report, Google Lunar XPRIZE, ATC Privatization

Also: Gustave Whitehead, AirVenture Innovation Preview, Learjet 75, HondaJet, ALEA, Honeywell, F-5N GAMA has published second quarter GA airplane shipment and billings data. The ge>[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2017 Web Development & Design by Pauli Systems, LC