Flight Testing Under Way For Third Block of C-5 Avionics | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.01.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-AffordableFlyers-04.18.24

Airborne-Unlimited-04.19.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Wed, Dec 17, 2003

Flight Testing Under Way For Third Block of C-5 Avionics

Better Avionics Functionality For America's Biggest Military Aircraft

Lockheed Martin and the Air Force have started flight testing the latest block of software developed for the C-5 Avionics Modernization Program (AMP). Testing began on Dec. 12 with a 4.8-hour flight from the company's facility here in an upgraded C-5B. Called Block 2.1, this is the third of four major software builds in the modernization program. It alone represents one third of the total amount of software code to be developed for AMP. More than 90 percent of the code to be developed for AMP is now in flight test.

"Block 2.1 brings a significant increase in functionality to the C-5's new digital avionics suite," said June Shrewsbury, Lockheed Martin's vice president of Strategic Airlift. "We have a structured plan in place where each new software block builds on what was accomplished previously. When we are done, the combination of hardware and software in AMP will allow Air Force crews to fly unrestricted anywhere in the world."

AMP replaces the analog cockpit instruments and systems in the C-5 with digital displays and equipment. It also provides the necessary communications and navigational avionics to comply with Global Air Traffic Management (GATM) requirements, the new set of international standards for aircraft movement and reduced separation in flight.

The Block 2.1 software, in addition to providing additional capability to the C-5's digital automatic flight control and flight management systems, adds the communications and navigation software necessary for basic GATM compliance.

A combined US Air Force and Lockheed Martin crew is scheduled to make a total of 19 flights from Dobbins ARB for Block 2.1 testing. The C-5B test aircraft is the same used for both the Block 1.1 and 1.2 test programs that concluded earlier this year. A modified C-5A that was first flown in the Block 1.2 test program also will be used during Block 2.1 testing.

The test program for Block 1.1, which was specifically limited in capability and provided the crew with the basic ability to aviate, navigate and communicate, was completed on March 7 after 10 flights and 44.8 flight hours. Block 1.1 accounted for 55 percent of the required AMP source lines of code. Flight testing of the Block 1.2 software, which provided additional capability, was completed on Sept. 10. Fifteen flights totaling 71 hours were made with 11 flights totaling 46.9 hours coming in the C-5B test aircraft, and four flights for 24.1 hours coming in the modified C-5A.

To handle software and hardware integration issues, Lockheed Martin has built a system integration laboratory that contains a hot mockup unit with the cockpit electronic boxes, the avionics interface units and the cockpit displays. Company and Air Force pilots are using a simulator with a 200- degree visual system as a development tool, helping engineers to find and potentially solve anomalies in the software as it is developed.

A number of developmental items overlap AMP and the second half of the C-5 modernization effort, the Reliability Enhancement and Re-engining Program (RERP). Capabilities that will be needed later specifically for RERP, such as an interface with the full-authority digital engine controller on the General Electric CF6 engine that will be installed on the C-5, are being included as part of the AMP software development effort now to lower total development costs.

Block 2.2 is the final block of AMP software to be developed. Containing roughly nine percent of the necessary source code, Block 2.2 is now in bench test and should be ready for flight by early 2004. Air Force operational test and evaluation of AMP is scheduled to begin in the third quarter of next year.

Earlier this year, Lockheed Martin was awarded a $20.3 million contract for the first eight AMP production kits. Once in production, it will take approximately two months to modify each aircraft. Fleet-wide AMP installation is expected to be complete in 2007.

FMI: www.lockheedmartin.com

Advertisement

More News

ANN's Daily Aero-Linx (04.16.24)

Aero Linx: International Business Aviation Council Ltd IBAC promotes the growth of business aviation, benefiting all sectors of the industry and all regions of the world. As a non->[...]

Aero-News: Quote of the Day (04.16.24)

"During the annual inspection of the B-24 “Diamond Lil” this off-season, we made the determination that 'Lil' needs some new feathers. Due to weathering, the cloth-cove>[...]

Airborne 04.10.24: SnF24!, A50 Heritage Reveal, HeliCycle!, Montaer MC-01

Also: Bushcat Woes, Hummingbird 300 SL 4-Seat Heli Kit, Carbon Cub UL The newest Junkers is a faithful recreation that mates a 7-cylinder Verner radial engine to the airframe offer>[...]

Airborne 04.12.24: SnF24!, G100UL Is Here, Holy Micro, Plane Tags

Also: Seaplane Pilots Association, Rotax 916’s First Year, Gene Conrad After a decade and a half of struggling with the FAA and other aero-politics, G100UL is in production a>[...]

Airborne-Flight Training 04.17.24: Feds Need Controllers, Spirit Delay, Redbird

Also: Martha King Scholarship, Montaer Grows, Textron Updates Pistons, FlySto The FAA is hiring thousands of air traffic controllers, but the window to apply will only be open for >[...]