Tinker Transformation Team Tackles Tech Troubles | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.01.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-Unlimited-04.11.24

Airborne-Unlimited-04.12.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Mon, Jan 26, 2009

Tinker Transformation Team Tackles Tech Troubles

F100 Engine Shop Lost Nearly $16 Million Before July '08

In July 2008, Mr. Brian deFonteny, Black Belt Center Transformation Office project facilitation, enlisted Michelle Waggoner, 547th Propulsion Maintenance Squadron industrial engineering technician, and her team -- Joseph Auzenne, Holly Vernon, Mitch Salvo, Shawna Price, Tracy Kudrna and John Manning -- to determine why the 76th Propulsion Maintenance Group's F100 engine Fan Blade Shop lost nearly $16 million during an 18-month period.

He also asked her to find a solution, using Air Force Smart Operations for the 21st Century tools, to keep it from happening again.

Not only did Ms. Waggoner and her team identify the root cause of the problem, but devised an action to significantly reduce costs. To date, the unit's ability to accurately execute the process is up by 40 percent.

"Supply management and parts integrity are a critical area of our business," Ms. Waggoner said. "Simple mistakes in procedure can cost the government and ultimately the taxpayers millions of dollars."

Prior to the discovery and fix, the team discovered fan blade shop personnel had over-ordered parts. As some parts were tested and calibrated, other pieces were ordered without the knowledge of everyone working on the engine. As a result, the actual replacement parts exceeded the projected replacement percentage.

To correct the problem, the team mapped the process, collected data and analyzed it. In doing so, they realized the true problem: the process of requesting, ordering and receiving fan blades and vanes.

"It was a very confusing process, and because of the previous ordering structure, over and under-ordering of required fan blades for each F100 engine was inevitable," Mr. deFonteny said.

Waggoner agreed.

"Nobody really knew what the process was," she said. "The process had been adjusted so many times, that special cause now became common cause. By mapping the entire process and performing data analysis, the broader picture became evident."

"After six weeks of very intense research, the light bulb finally came on," Ms. Waggoner said.

Ms. Waggoner said there were a lot of assumptions made as to how parts were ordered. Because the material issue request form is not electronically processed, there were several risks inherent with processing the paper request. They include the copy getting lost, damaged, destroyed by a liquid spill and not duplicated, more than one form is completed for a part or the paper is lost in transit.

By eliminating the number of requests processed throughout the procedure, Ms. Waggoner said, the number of errors that could occur dropped from five times to just two.

"This was not just people randomly inserting hunches for fixes," Mr. deFonteny said. "It was a very structured data-driven AFSO21 project resulting from the training received here at Tinker."

Ms. Waggoner said although a significant improvement was made, the key is to monitor the processes and make sure shop personnel remain focused on the revised course of action.

"I hope the culture of continuous improvement becomes ingrained, because there's always room for improvement," said Waggoner.

FMI: www.af.mil

Advertisement

More News

ANN's Daily Aero-Linx (04.16.24)

Aero Linx: International Business Aviation Council Ltd IBAC promotes the growth of business aviation, benefiting all sectors of the industry and all regions of the world. As a non->[...]

Aero-News: Quote of the Day (04.16.24)

"During the annual inspection of the B-24 “Diamond Lil” this off-season, we made the determination that 'Lil' needs some new feathers. Due to weathering, the cloth-cove>[...]

Airborne 04.10.24: SnF24!, A50 Heritage Reveal, HeliCycle!, Montaer MC-01

Also: Bushcat Woes, Hummingbird 300 SL 4-Seat Heli Kit, Carbon Cub UL The newest Junkers is a faithful recreation that mates a 7-cylinder Verner radial engine to the airframe offer>[...]

Airborne 04.12.24: SnF24!, G100UL Is Here, Holy Micro, Plane Tags

Also: Seaplane Pilots Association, Rotax 916’s First Year, Gene Conrad After a decade and a half of struggling with the FAA and other aero-politics, G100UL is in production a>[...]

Airborne-Flight Training 04.17.24: Feds Need Controllers, Spirit Delay, Redbird

Also: Martha King Scholarship, Montaer Grows, Textron Updates Pistons, FlySto The FAA is hiring thousands of air traffic controllers, but the window to apply will only be open for >[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC