Lockheed To Speed Development Of Joint Strike Fighter | Aero-News Network
Aero-News Network
RSS icon RSS feed
podcast icon MP3 podcast
Subscribe Aero-News e-mail Newsletter Subscribe

Airborne Unlimited -- Most Recent Daily Episodes

Episode Date

Airborne-Monday

Airborne-Tuesday

Airborne-Wednesday Airborne-Thursday

Airborne-Friday

Airborne On YouTube

Airborne-Unlimited-04.01.24

Airborne-Unlimited-04.16.24

Airborne-FlightTraining-04.17.24 Airborne-Unlimited-04.11.24

Airborne-Unlimited-04.12.24

Join Us At 0900ET, Friday, 4/10, for the LIVE Morning Brief.
Watch It LIVE at
www.airborne-live.net

Sat, Mar 06, 2010

Lockheed To Speed Development Of Joint Strike Fighter

Program Was Nearing Possible "Nunn-McCurdy" Cancellation Deadline

Defense Department leaders and Lockheed Martin executives explained changes that have been made in the Joint Strike Fighter program to their international partners this week. Ashton B. Carter, the department's undersecretary for acquisition, technology and logistics, and Robert Stevens, chief operating officer for Lockheed Martin, the prime contractor for the program, explained what measures Defense Secretary Robert M. Gates has taken to right the program.

A department study of the program completed in October found the development phase of the revolutionary aircraft had slipped by 30 months. Gates has made changes that will reduce the slippage to 13 months, Carter said Thursday.  He was able to report to the partners that the Joint Strike Fighter program now has a realistic plan and "not a blindly optimistic one" or a "fatalistic one."

The undersecretary also said the study identified management measures to improve performance over the coming years. "I want to emphasize that this process of independent review and aggressive management to specific milestones will continue," he said.

Carter emphasized that the review turned up no fundamental technological or manufacturing problems with the JSF program and no failure to make military capabilities. He reiterated that the Joint Strike Fighter will be the backbone of collective air superiority for the next generation.

The report showed the JSF program was taking longer and costing more than either the government development office or the contractor had predicted, Carter said. "This schedule and cost trend was unacceptable for the taxpayers of the U.S. and for the other eight nations," he said. "The schedule slip was estimated at 30 months in the development program. The cost of the airplanes had grown since 2002 and that for a variety of reasons the JSF program would breach the Nunn-McCurdy threshold." The Nunn-McCurdy law requires that Congress be notified of a cost growth of more than 15 percent in a program. It also calls for cancellation of programs for which total cost grew by more than 25 percent over the original estimate.

"We didn't wait for the Nunn-McCurdy paperwork to play out," the undersecretary said. "We began to review and restructure the JSF program as though it were already in Nunn-McCurdy breach and the results of that review and restructuring were subsequently described by Gates."

Gates announced the restructuring of the JSF program, which is the most expensive acquisition in U.S. military history, in early February. The objective is to restore the schedule in the development program. "We assessed that this was feasible and was possible to reduce the slip in the development program from 30 months to 13 months and that we could realistically plan on that basis provided we took some immediate management steps," Carter said. That means procuring one more carrier variant aircraft and additional regular aircraft to conduct flight testing "with the idea of hastening the completion of the program," he said.

The changes also call for development of aircraft software capability. "All of these steps were directed in the restructuring and that's the first steps in the effort to buy back some of the slips in the development program," Carter said.

The defense secretary did not believe it was reasonable for the customers to bear all the costs of those actions, and decided DoD would withhold $614 million of the award fee from the contract, Carter said. "We will be adjusting contract structures in the future to align contractor performance to what we need," he said.

The restructuring allows for contractors to adopt a more realistic schedule and production ramp, and gives Lockheed Martin and subcontractors every opportunity "to accelerate production and make affordable aircraft, faster," he said.

FMI: www.lockheedmartin.com

Advertisement

More News

ANN's Daily Aero-Linx (04.15.24)

Aero Linx: International Flying Farmers IFF is a not-for-profit organization started in 1944 by farmers who were also private pilots. We have members all across the United States a>[...]

Classic Aero-TV: 'No Other Options' -- The Israeli Air Force's Danny Shapira

From 2017 (YouTube Version): Remembrances Of An Israeli Air Force Test Pilot Early in 2016, ANN contributor Maxine Scheer traveled to Israel, where she had the opportunity to sit d>[...]

Aero-News: Quote of the Day (04.15.24)

"We renegotiated what our debt restructuring is on a lot of our debts, mostly with the family. Those debts are going to be converted into equity..." Source: Excerpts from a short v>[...]

Airborne 04.16.24: RV Update, Affordable Flying Expo, Diamond Lil

Also: B-29 Superfortress Reunion, FAA Wants Controllers, Spirit Airlines Pulls Back, Gogo Galileo Van's Aircraft posted a short video recapping the goings-on around their reorganiz>[...]

ANN's Daily Aero-Term (04.16.24): Chart Supplement US

Chart Supplement US A flight information publication designed for use with appropriate IFR or VFR charts which contains data on all airports, seaplane bases, and heliports open to >[...]

blog comments powered by Disqus



Advertisement

Advertisement

Podcasts

Advertisement

© 2007 - 2024 Web Development & Design by Pauli Systems, LC